Phase I: 2008-2009
In This Section
Goal
The Phase I Development Plan was to transform the former trailer campground into a site capable of supporting our first year running our summer camp program.
Timeline
Phase I began when we purchased the property in August 2008, and was completed by July 2009.
Objectives
- Upgrade the existing water purification system to meet provincial standards for children’s summer camps
- Build 10 camper cabins in two separate areas for boys and girls
- Build two additional washhouses for the cabin areas (cost: $4,000)
- Convert the existing White Owl Lodge into a temporary kitchen, including a walk-in cooler and commercial dishwasher
- Reroute the existing access road for our neighboring cottages
- Purchase or borrow needed activity supplies, such as kayaks, lifejackets, archery and woodworking equipment
- Borrow a marquee tent for use as a temporary dining hall.
At A Glance
| Item | Estimated Cost | Status |
| Water purification system | $40,000 | Completed! |
| Construction of 10 new cabins | $100,000 | Completed! |
| Two new washhouses | $4,000 | Completed! |
| Temporary kitchen conversion (walk-in fridge, dishwasher, freezers) | $10,000 | Completed! |
| New access road development | $6,000 | Completed! |
| Activity supplies: kayaks, lifejackets, archery equipment, woodworking equipment | $5,000 | Completed! |
Check It Out
- Check our Construction Blog for the day-by-day progress reports as we worked together to build the new facilities during Spring Build Weekends starting in April 2009.
- Check out our Photo Gallery for additional pictures of the new camp facilities.
- Donate or attend a fundraising event to help us raise money to cover the cost of the next phase of development.